Marchés publics : indemnisation des conséquences du retard dans l'exécution d'un marché

Public procurement: compensation for the consequences of delay in the performance of a contract

by gmorales on August 1, 2012 | Category: Public markets
Marchés publics : indemnisation des conséquences du retard dans l'exécution d'un marché Marchés publics : indemnisation des conséquences du retard dans l'exécution d'un marché

CE 1st of August 2012, Sté SCARPARI, Req. No. 342337

The holder of a public contract is entitled to full compensation for the damage he has suffered as a result of delays in performance of the contract attributable to the contracting authority or his other co-contractors and distinct from the lengthening of the contract. the duration of the work due to the completion of the additional work, since this damage appears certain and presents with these delays a direct causal link. The applicant company does not have to produce a contractual timetable to quantify the delay attributable to the owner of the work as soon as the contractual period is fixed by the parts of the market. The revision of the prices is of right for the services carried out outside contractual deadlines